Requirements for cold performance test before initial fuel loading of pressurized water reactor nuclear power plants
| Valid |
GB/T 41587-2022
|
PDF similar to GB/T 41587-2022
Basic data Standard ID | GB/T 41587-2022 (GB/T41587-2022) | Description (Translated English) | Requirements for cold performance test before initial fuel loading of pressurized water reactor nuclear power plants | Sector / Industry | National Standard (Recommended) | Classification of Chinese Standard | F63 | Word Count Estimation | 9,938 | Issuing agency(ies) | State Administration for Market Regulation, China National Standardization Administration |
GB/T 41587-2022: Requirements for cold performance test before initial fuel loading of pressurized water reactor nuclear power plants ---This is a DRAFT version for illustration, not a final translation. Full copy of true-PDF in English version (including equations, symbols, images, flow-chart, tables, and figures etc.) will be manually/carefully translated upon your order.
Requirements for cold performance test before initial fuel loading of pressurized water reactor nuclear power plants
ICS 27.120.20
CCSF63
National Standards of People's Republic of China
Requirements for cold state performance test before charging of pressurized water reactor nuclear power plant
Published on 2022-07-11
2023-02-01 Implementation
State Administration for Market Regulation
Released by the National Standardization Administration
directory
Preface III
1 Scope 1
2 Normative references 1
3 Terms and Definitions 1
4 Test conditions 1
5 Test content 2
6 Acceptance criteria5
7 Test records and reports 5
foreword
This document is in accordance with the provisions of GB/T 1.1-2020 "Guidelines for Standardization Work Part 1.Structure and Drafting Rules of Standardization Documents"
drafted.
Please note that some content of this document may be patented. The issuing agency of this document assumes no responsibility for identifying patents.
This document is proposed and managed by the National Nuclear Energy Standardization Technical Committee (SAC/TC58).
This document is drafted by. China Nuclear Power Engineering Co., Ltd., China General Nuclear Power Engineering Co., Ltd., Shanghai Nuclear Engineering Research and Design Institute Co., Ltd.
The main drafters of this document. Xing Ji, Tian Qiwei, Sun Tao, Liu Yong, Yu Decheng, Zhang Xiang, Wang Wenhua, Li Yinglin, Wu Jiabin, Zhou Xingqiang,
Li Pengfei and Feng Jia.
Requirements for cold state performance test before charging of pressurized water reactor nuclear power plant
1 Scope
This document specifies the test conditions, test contents, acceptance criteria and test records for the cold performance test before initial fuel loading of PWR nuclear power plants
and report.
This document is applicable to the cold performance test before the initial fuel loading of the pressurized water reactor nuclear power plant.
2 Normative references
The contents of the following documents constitute essential provisions of this document through normative references in the text. Among them, dated citations
documents, only the version corresponding to that date applies to this document; for undated references, the latest edition (including all amendments) applies to
this document.
GB/T 28548-2012 Technical Guidelines for Hydrostatic Test of Main Circuit of Nuclear Power Plant
NB/T.20145 Nuclear power plant commissioning test procedures and report writing specifications
3 Terms and Definitions
The following terms and definitions apply to this document.
3.1
Debug commissioning
The process of operating installed nuclear power plant components and systems and verifying that their performance conforms to design requirements and related criteria.
Note. Commissioning includes tests without nuclear reactions and with nuclear reactions.
3.2
coldperformancetest
Initial start-up of fluid systems and support systems to obtain initial operating data of equipment, operational compatibility with connected systems, and verification of this
some system functions.
4 Test conditions
The test conditions of the cold state performance test before charging mainly include.
a) The organizational structure, division of responsibilities, human resources, planning and administrative management have been arranged;
b) The staffing and training meet the requirements, and the personnel have passed the necessary qualification review and have been authorized;
c) The debugging file has taken effect;
d) The test schedule has been formulated, and each item of the cold performance test can be carried out in an orderly and controlled manner;
e) structures, systems and components have been installed in accordance with design requirements and technical conditions;
f) Before the cold performance test, the function of the equipment, subsystem or component has been verified, and the system is in a state suitable for starting the test;
g) The combined flushing of the single system and the nuclear steam supply system has been completed;
h) Mechanical equipment, electrical equipment and instrumentation and control equipment have been inspected and meet the test requirements;
i) Data acquisition, data analysis and control functions meet the design requirements;
Tips & Frequently Asked Questions:Question 1: How long will the true-PDF of GB/T 41587-2022_English be delivered?Answer: Upon your order, we will start to translate GB/T 41587-2022_English as soon as possible, and keep you informed of the progress. The lead time is typically 1 ~ 3 working days. The lengthier the document the longer the lead time. Question 2: Can I share the purchased PDF of GB/T 41587-2022_English with my colleagues?Answer: Yes. The purchased PDF of GB/T 41587-2022_English will be deemed to be sold to your employer/organization who actually pays for it, including your colleagues and your employer's intranet. Question 3: Does the price include tax/VAT?Answer: Yes. Our tax invoice, downloaded/delivered in 9 seconds, includes all tax/VAT and complies with 100+ countries' tax regulations (tax exempted in 100+ countries) -- See Avoidance of Double Taxation Agreements (DTAs): List of DTAs signed between Singapore and 100+ countriesQuestion 4: Do you accept my currency other than USD?Answer: Yes. If you need your currency to be printed on the invoice, please write an email to [email protected]. In 2 working-hours, we will create a special link for you to pay in any currencies. Otherwise, follow the normal steps: Add to Cart -- Checkout -- Select your currency to pay.
|