Technical specification for application and issuance of pollutant permit - Ferroalloy and electrolytic manganese industry
| Valid |
HJ 1117-2020
|
Standard similar to HJ 1117-2020 HJ 1108 HJ 1109 HJ 1107
Basic data | Standard ID | HJ 1117-2020 (HJ1117-2020) | | Description (Translated English) | Technical specification for application and issuance of pollutant permit - Ferroalloy and electrolytic manganese industry | | Sector / Industry | Environmental Protection Industry Standard | | Word Count Estimation | 115,157 | | Date of Issue | 2020-03-04 | | Date of Implementation | 2020-03-04 | | Issuing agency(ies) | Ministry of Ecology and Environment |
HJ 1117-2020: Technical specification for application and issuance of pollutant permit - Ferroalloy and electrolytic manganese industry ---This is a DRAFT version for illustration, not a final translation. Full copy of true-PDF in English version (including equations, symbols, images, flow-chart, tables, and figures etc.) will be manually/carefully translated upon your order.
Technical specification for application and issuance of pollutant permit - Ferroalloy and electrolytic manganese industry
National Environmental Protection Standards of the People's Republic of China
Technical specifications for pollutant discharge permit application and issuance
Ferroalloy, Electrolytic Manganese Industry
2020-0 3-0 4 released
2020-0 3-0 4 Implementation
Issued by the Ministry of Ecology and Environment
Table of contents
Foreword...II
Part 1 Ferroalloy Sewage Unit...1
1 Scope of application...1
2 Normative references...1
3 Terms and definitions...2
4 Key management pollutant discharge units...3
5 Simplify the management of sewage units...29
Part 2 Electrolytic Manganese Discharge Unit...48
1 Scope of application...48
2 Normative references...48
3 Terms and definitions...49
4 Key pollution management units...49
5 Simplify the management of sewage units...69
Appendix A (informative appendix) RKEF process sulfur dioxide, nitrogen oxides permitted emission limit recommended method...83
Appendix B (Informative Appendix) Reference Table of Available Technologies for Waste Gas and Wastewater Pollution Control...84
Appendix C (Informative Appendix) Environmental Management Ledger Records (Key Management Pollutant Discharge Units)...86
Appendix D (Informative Appendix) Form of Annual Implementation Report of Pollution Discharge Permit (Key Management Pollutant Discharge Units)...90
Appendix E (Informative Appendix) Environmental Management Ledger Records (Simplified Management of Pollutant Discharge Units)...104
Appendix F (Informative Appendix) Form of Annual Implementation Report of Pollution Discharge Permit (Simplified Management of Pollution Discharge Units)...106
Foreword
In order to implement the "Environmental Protection Law of the People's Republic of China", "The Air Pollution Prevention Law of the People's Republic of China", "China
The Water Pollution Prevention and Control Law of the People’s Republic of China, the Soil Pollution Prevention and Control Law of the People’s Republic of China and other laws and regulations, and the State Council
Notice of the General Office on Issuing the Implementation Plan of the Permit System for Controlling Pollutant Discharge (Guobanfa [2016] No. 81) and the
Measures for the Administration of Pollution Permits (for Trial Implementation)" (Ministry of Environmental Protection Order No. 48), improving the technical support system
To guide and standardize the application and issuance of pollutant discharge permits of ferroalloy and electrolytic manganese pollutants, and formulate this standard.
This standard specifies the basic requirements for filling in the application and issuance of pollutant discharge permits for ferroalloy and electrolytic manganese pollutants
Determination of emission limits, calculation of actual emissions, methods for compliance determination, self-monitoring, environmental management ledgers, and emission permits
Environmental management requirements such as the certifiable implementation report, and proposed reference requirements for feasible technologies for pollution prevention and control.
Appendix A to Appendix F of this standard are informative appendices.
This standard is issued for the first time.
This standard is formulated by the Department of Environmental Impact Assessment and Emission Management and the Department of Regulations and Standards of the Ministry of Ecology and Environment.
The main drafting organizations of this standard. Environmental Engineering Evaluation Center of Ministry of Ecology and Environment, Chinese Academy of Environmental Sciences, Metallurgical Industry
Planning Research Institute, MCC Dongfang Engineering Technology Co., Ltd., China Ferroalloy Industry Association.
This standard was approved by the Ministry of Ecology and Environment on March 04, 2020.
This standard will be implemented on March 04, 2020.
This standard is interpreted by the Ministry of Ecology and Environment.
Pollutant discharge permit application and issuance of technical specifications for ferroalloy and electrolytic manganese industries
Part One Ferroalloy Sewage Unit
1 Scope of application
This standard specifies the basic requirements for filling out the application and issuance of a pollutant discharge permit by ferroalloy pollutants, as well as the permitted discharge limit.
Value determination, actual emissions accounting, compliance determination methods, self-monitoring, environmental management ledger and emission permit implementation
Environmental management requirements such as reports put forward feasible technical requirements for pollution prevention and control.
This standard is applicable to guide ferroalloy pollutants to fill in the "Sewage Discharge Permit Application Form" and to manage pollutant discharge permits nationwide
Fill in the relevant application information in the information platform application system, which is suitable for guiding the issuing authority to review and determine the sewage discharge of the ferroalloy sewage discharge unit
License requirements.
This standard is applicable to the permit management of air pollutants and water pollutants discharged by ferroalloy pollutants. Ferroalloy row
Among the pollutants, the sintering machines and pellets that implement the "Emission Standard for Air Pollutants from the Iron and Steel Sintering and Pelletizing Industry"
For production facilities and discharge outlets such as group roasting, the "Technical Specifications for the Application and Issuance of Pollutant Discharge Permits" (HJ 846) shall apply;
The production facilities and discharge outlets that implement the "Boiler Air Pollutant Emission Standard" (GB 13271) are applicable to the "Sewage Discharge Permit"
Application and issuance of technical specifications for boilers (HJ 953).
Ferroalloys that are not specified in this standard but emit industrial waste water, exhaust gas or toxic and harmful air pollutants specified by the state
Other production facilities and discharge outlets of the pollutant discharge unit shall be implemented in accordance with the "General Rules for the Application and Issuance of Pollutant Discharge Permits" (HJ 942).
2 Normative references
The content of this standard refers to the following documents or their clauses. For undated references, the valid version
Applies to this standard.
GB 8978 Integrated Wastewater Discharge Standard
GB 9078 Emission Standard of Air Pollutants for Industrial Furnaces
GB 13271 Boiler Air Pollutant Emission Standard
GB 13456 Discharge standard of water pollutants for iron and steel industry
GB 28662 Emission Standard of Air Pollutants for Iron and Steel Sintering and Pelletizing Industry
GB 28663 Air Pollutant Emission Standard for Ironmaking Industry
GB 28664 Air Pollutant Emission Standard for Steelmaking Industry
GB 28666 Pollutant Emission Standard for Ferroalloy Industry
GB/T 16157 Determination of particulate matter in exhaust from stationary sources and sampling method for gaseous pollutants
HJ 75 Technical Specification for Continuous Monitoring of Smoke Emission from Stationary Pollution Sources (Trial)
HJ 76 Technical requirements and testing methods for continuous monitoring system of flue gas emissions from stationary sources (for trial implementation)
HJ 91.1 Technical Specification for Wastewater Monitoring
HJ 494 Technical Guide for Water Quality Sampling
HJ 495 Technical Regulations for Water Quality Sampling Scheme Design
HJ 521 Wastewater Discharge Law Code (Trial)
HJ 608 Code Rules for Pollutant Discharge Units
HJ 819 General Rules of Technical Guidelines for Self-monitoring of Pollutant Discharge Unit
HJ 846 Technical Specification for the Application and Issuance of Pollution Discharge Permits for the Iron and Steel Industry
HJ 942 General Rules of Technical Specifications for Pollution Discharge Permit Application and Issuance
HJ 944 General Rules of Technical Specification for Environmental Management Ledger and Pollution Discharge Permit Implementation Report (Trial)
HJ 953 Sewage discharge permit application and issuance of technical specifications for boilers
HJ/T 55 Technical Guidelines for Monitoring Unorganized Emissions of Air Pollutants
HJ/T 91 Technical specification for surface water and sewage monitoring
HJ/T 353 Water Pollution Source Online Monitoring System Installation Technical Specification (Trial)
HJ/T 354 Technical Specification for Acceptance of Online Water Pollution Source Monitoring System (Trial)
HJ/T 355 Water Pollution Source Online Monitoring System Operation and Assessment Technical Specification (Trial)
HJ/T 356 Technical Specification for Data Validity Judgment of Online Water Pollution Source Monitoring System (Trial)
HJ/T 397 Fixed source exhaust gas monitoring technical specification
"Administrative Measures for Pollution Discharge Permits (Trial)" (Ministry of Environmental Protection Order No. 48)
"List of Classification Management of Discharge Permits for Fixed Pollution Sources"
"Notice of the State Council on Printing and Distributing the Three-Year Action Plan for Winning the Blue Sky Defense War" (Guo Fa [2018] No. 22)
"Announcement on the Implementation of Special Emission Limits for Air Pollutants" (Announcement No. 14 of.2013)
"Technical Requirements for Standardized Remediation of Sewage Outlets (Trial)" (Environmental Supervision of the State Environmental Protection Administration [1996] No. 470)
"Reply to Issues Concerning the Implementation of Special Emission Limits for Air Pollutants" (Huanban Qiqihan [2016] No. 1087)
"Notice on Strengthening the Automatic Monitoring of Beijing-Tianjin-Hebei Elevated Source Pollutants" (Huanban Huanjianhan [2016] No. 1488)
"Announcement on the Implementation of Special Emission Limits for Air Pollutants in Beijing-Tianjin-Hebei Air Pollution Transmission Channel Cities" (Environmental Protection
Ministry of Health Announcement No. 9 of.2018)
"Comprehensive Treatment Plan for Air Pollution in Industrial Furnaces" (Huan Qiqi [2019] No. 56)
3 Terms and definitions
The following terms and definitions apply to this standard.
3.1 ferroalloy pollutant emission unit
Refers to smelting enterprises or facilities that use electric furnace method, blast furnace method, converter method, and out-of-furnace method (metal thermal method) to produce ferroalloys.
3.2 smelting method of electric furnace
Refers to the process of using reduction electric furnaces (submerged arc furnaces) and refining furnaces to produce ferroalloy products.
3.3 permitted emission limits
Refers to the maximum discharge concentration and maximum discharge volume of pollutants that are allowed to be discharged by the pollutant discharge unit specified in the pollution discharge permit.
3.4 special periods
Refers to the pollutant discharge situation of the pollutant discharging unit in accordance with the national and local standards-compliant plans and other relevant environmental management regulations.
Periods with special requirements for conditions, including heavy pollution weather response periods and winter protection periods.
4 Key management pollutant discharge units
4.1 Requirements for the declaration of the basic situation of pollutants
4.1.1 General principles
Ferroalloy pollutant discharge units shall, in accordance with the requirements of this standard, fill in the relevant information in the national pollutant discharge permit management information platform application system.
Should information table. Local ecological and environmental authorities at or above the municipal level with districts may, in accordance with local regulations, increase the
The content specified in the permit, and fill in the “local ecological
Management content added by environmental authorities" column.
4.1.2 Basic information of pollutant discharge units
The basic information of the pollutant discharge unit should be filled in with the name of the unit, the management category of pollution discharge permit, the postal code, and the industry category (fill in
When selecting ferroalloys to smelt C314 ferroalloys), whether to put into production, the date of putting into
The central latitude of the business site, whether the location is an environmentally sensitive area (such as a key atmospheric control area, a total phosphorus and total nitrogen control area, etc.),
The name of the industrial park to which it belongs, whether there is an environmental assessment approval document and document number (record number), whether there is a local government’s
The identification or filing document and document number, whether there is a major pollutant total distribution plan document and document number, and the total particulate matter indicator
(T/a), total sulfur dioxide indicator (t/a), total nitrogen oxide indicator (t/a), total chemical oxygen demand indicator (t/a),
Total ammonia nitrogen indicator (t/a), total indicators of other pollutants involved (if any), etc.
4.1.3 Main products and production capacity
4.1.3.1 General principles
When reporting “main products and production capacity”, the pollutant discharge unit shall report the main production unit, production process, and main production equipment.
Installation, facility number, facility parameters, product name, production capacity and unit of measurement, design year production time and other options, etc.
information.
4.1.3.2 Main production units, main processes, production facilities and facility parameters
When reporting "main products and capacity", select "ferroalloy". The main production unit, main
See Table 1 for the filling content of process, production facilities and facility parameters.
4.1.3.3 Production facility number
The ferroalloy pollutant discharge unit shall fill in the internal production facility number. If the ferroalloy pollutant discharge unit does not have the internal production facility number, it shall be
Number and fill in according to HJ 608.
4.1.3.4 Product name
Ferrosilicon, manganese silicon, high-carbon ferromanganese, medium and low carbon ferromanganese, high-carbon ferrochrome, medium and low carbon ferrochrome, silicon-chromium alloy, silicon-calcium alloy,
Ferronickel, ferromolybdenum, silicon aluminum alloy, silicon barium alloy, and others.
4.1.3.5 Production capacity and measurement unit
Production capacity and unit of measurement are required. Production capacity is the design capacity of the main product, excluding national or local governments
Capacity to be eliminated or banned. The unit of measurement for production capacity and output is 10,000 t/a.
4.1.3.6 Design year production time
According to the annual production in the environmental impact assessment documents and approval opinions or the local government’s identification of illegal projects or the filing documents
Fill in time. If there are no approval opinions, confirmation or filing documents, fill in the actual annual production time.
4.1.3.7 Other
If the pollutant discharge unit has other content that needs to be explained, it can be filled in.
4.1.4 Main raw and auxiliary materials
4.1.4.1 Main raw and auxiliary materials and fuel types
The types of raw materials include silica, chrome ore, laterite nickel ore, manganese ore, sintered ore, pellets, coke, blue carbon, manganese-rich slag,
Metal reducing agent, others.
The types of accessories include limestone, dolomite, fluorite, electrode paste, and others.
Fuel types include coal, heavy oil, natural gas, oil, and others.
4.1.4.3 Sulfur elements, toxic and harmful components of raw materials
It is necessary to fill in toxic and hazardous substances or elements such as sulfur and heavy metals in raw materials and auxiliary materials according to the design value or the actual production value of the previous year.
Ingredients and proportions.
4.1.4.4 Fuel composition
It is necessary to fill in the fuel ash and sulfur content according to the design value or the actual production value of the previous year (solid and liquid fuels are calculated according to the sulfur content; gas
Fuel is based on total sulfur, which includes organic sulfur and inorganic sulfur), volatile matter and calorific value (low calorific value), fuel oil and gas
Write sulfur content and calorific value. The reported value is based on the received basis.
4.1.4.5 Other
If the pollutant discharge unit needs to explain, it can be filled in.
4.1.5 Pollutant production and discharge nodes, major pollutants and pollution control facilities
4.1.5.1 General principles
Waste gas production and discharge nodes, pollutants and pollution control facilities include the names of corresponding pollution production links, pollutant items, and emission patterns.
Type (organized, unorganized), pollution control facilities, whether it is a feasible technology, organized discharge port number, discharge port setting
Whether it meets the requirements and the type of discharge port.
Wastewater production and discharge nodes, pollutants and pollution control facilities, including waste water categories, pollutant items, discharge destinations, and discharge
Rules, pollution control facilities, discharge port numbers, whether discharge port settings meet requirements, and discharge port types.
4.1.5.2 Exhaust gas
a) Name of waste gas pollution link, pollutant items, emission form and pollution control facilities
Names of waste gas production links, pollutant items, emission forms, and pollution control facilities
The content of the report is shown in Table 2.Waste gas pollutants from electric furnace smelting are determined according to GB 28666; waste gas pollutants from blast furnace smelting
The project is determined in accordance with GB 28662 and GB 28663; the waste gas pollutant project of converter method smelting is determined in accordance with GB 28664;
Waste gas pollutants from French smelting are determined in accordance with GB 9078; waste gas pollutants from other pollution sources are determined in accordance with GB 28666.
Where there are local emission standards, it shall be determined in accordance with the local emission standards.
b) Number of pollution prevention facilities and organized discharge outlets
The number of pollution prevention facilities can be filled with the internal number of the pollutant discharge unit. If the pollutant discharge unit does not have an internal number, it shall be based on HJ 608
Number and fill in.
The number of the organized discharge outlet shall be filled in with the existing number of the local ecological and environmental authority or shall be carried out by the pollutant discharge unit according to HJ 608
Number and fill in.
c) Requirements for setting the discharge port
According to the "Technical Requirements for Standardized Remediation of Sewage Outlets (Trial)" and the relevant emission standards in the emission standards implemented by the
Regarding the regulation of standardized setting of vents, report whether the setting of exhaust gas discharge outlets meets the standardized requirements. Where there are stricter requirements,
Follow its regulations.
d) Type of emission
The waste gas discharge outlets of the key management ferroalloy pollutants are divided into main discharge ports and general discharge ports. Main discharge outlets include electricity
Furnace method smelting raw material system roasting flue gas discharge port, semi-closed submerged arc furnace exhaust gas discharge port (except for ferrosilicon production), blast furnace method
Smelting blast furnace smelting waste gas discharge port, blast furnace method smelting blast furnace tapping yard exhaust gas discharge port, converter method smelting converter flue gas discharge port.
Except for the main discharge ports, all are general discharge ports.
4.1.5.3 Wastewater
a) Wastewater category, pollutant items and pollution control facilities
Refer to Table 3 for the types of wastewater, pollutant items, and pollution control facilities for the key management ferroalloy pollutants. high
Wastewater pollutants from furnace smelting are determined in accordance with GB 13456, and wastewater pollutants from other smelting projects are determined in accordance with GB 28666
If it is confirmed that there are local emission standards, it shall be determined in accordance with the local emission standards.
b) Emission destination and emission law
The ferroalloy pollutant discharge unit shall clarify the destination and discharge rules of wastewater discharge.
Emission destinations include no emissions, direct emissions and indirect emissions.
Non-discharge refers to the reuse of wastewater after treatment, and other methods that are not discharged to the environment.
Direct discharge refers to directly entering the water environment such as rivers, lakes, reservoirs, etc., directly entering the sea and entering the city after being processed in the factory.
City sewer (reenter rivers, lakes, reservoirs), urban sewer (reenter coastal waters), and other direct access
Discharge methods of environmental water bodies.
Indirect discharge refers to entering urban sewage treatment plants, entering other units, entering industrial wastewater centralized treatment facilities, and other
He indirectly enters the discharge method of environmental water bodies.
Fill in the discharge rule for direct or indirect discharge of wastewater, and do not need to fill in if it is not discharged. Refer to HJ 521 for waste water discharge rules.
c) Requirements for setting the discharge port
According to the "Technical Requirements for Standardized Remediation of Sewage Outlets (Trial)" and the relevant emission standards in the emission standards implemented by the
Regarding the regulation of standardized setting of venting, fill in whether the setting of wastewater discharge outlet meets the standardized requirements.
d) Type of discharge port
The waste water discharge outlets of ferroalloy pollutants are all general discharge outlets.
4.1.6 Drawing requirements
The basic situation of the pollutant discharge unit should also include the production process flow chart (including the whole plant and each process), the layout plan of the plant area,
Layout plan of rainwater and sewage pipe network.
The production process flow chart should at least include the main production facilities (equipment), the flow of main raw materials and fuels, and the production process flow.
The layout plan of the plant area should at least include the main facilities, public and auxiliary facilities, waste gas treatment facilities, wastewater treatment facilities, sewage
Treatment facilities, temporary storage warehouses for hazardous wastes, etc., and indicate the main exhaust outlets, general exhaust outlets, and production units for unorganized emissions.
The layout of rainwater and sewage pipe network should include the direction of rainwater and sewage collection and transportation pipelines in the plant area, the location of discharge outlets and the discharge destination, etc.
content.
4.1.7 Other requirements
Failed to obtain the approval opinions of the construction project environmental impact assessment documents or approved by the local people’s government in accordance with relevant regulations.
The pollution control facilities or measures adopted by the pollutant discharging units that deal with and rectify the normative and relevant certification materials that meet the requirements
To the pollutant discharge unit that requires the permitted emission concentration, and the pollutant discharge unit that has other actions that need to be corrected in accordance with the regulations, in the first declaration
When filling in the application information for pollutant discharge permits, the “Correction Regulations” in the national pollutant discharge permit management information platform application system
Column, propose a correction plan.
4.2 Corresponding discharge outlets of production and discharge links and methods for determining permitted discharge limits
4.2.1 Production and discharge links and corresponding discharge outlets
4.2.1.1 Exhaust gas
The key management of ferroalloy pollutant emission units' waste gas production and discharge nodes and corresponding discharge outlets are shown in Table 2.
Exhaust gas outlets should be filled with the geographical coordinates of the outlet, the height of the exhaust cylinder, the inner diameter of the exhaust cylinder, and the national or local pollutant emissions
Standards, environmental impact assessment approval opinions, requirements and commitments to stricter emission limits.
4.2.1.2 Wastewater
See...
|