Technical requirements for simulation test of control system functions of the rural photovoltaic power station cluster
| Valid |
GB/T 40616-2021
|
PDF similar to GB/T 40616-2021
Basic data Standard ID | GB/T 40616-2021 (GB/T40616-2021) | Description (Translated English) | Technical requirements for simulation test of control system functions of the rural photovoltaic power station cluster | Sector / Industry | National Standard (Recommended) | Classification of Chinese Standard | F12 | Word Count Estimation | 16,138 | Issuing agency(ies) | State Administration for Market Regulation, China National Standardization Administration |
GB/T 40616-2021: Technical requirements for simulation test of control system functions of the rural photovoltaic power station cluster ---This is a DRAFT version for illustration, not a final translation. Full copy of true-PDF in English version (including equations, symbols, images, flow-chart, tables, and figures etc.) will be manually/carefully translated upon your order.
Technical requirements for simulation test of control system functions of the rural photovoltaic power station cluster
ICS 27.160
CCSF12
National Standards of People's Republic of China
Simulation test of cluster control system of photovoltaic power station in villages and towns
skills requirement
Released on 2021-10-11
2022-05-01 implementation
State Administration of Market Supervision and Administration
Issued by the National Standardization Management Committee
Table of contents
Foreword Ⅲ
1 Scope 1
2 Normative references 1
3 Terms and definitions 1
4 Basic rules 1
5 Test item 1
5.1 Monitoring master station test item 1
5.2 Monitoring terminal test item 2
6 Test system 2
6.1 General requirements 2
6.2 Functional requirements of the simulation test system 2
6.3 Performance requirements of simulation test system 3
7 Test steps and result judgment 3
7.1 Cluster monitoring master station function test 3
7.2 Monitoring terminal function test 6
Appendix A (informative) The overall architecture of the simulation test system for the cluster control system of the village and town photovoltaic power station 8
Appendix B (Informative) Simulation Test Record Form 9 of Village and Township Photovoltaic Power Station Cluster Control System
Appendix C (Informative) Village and Township Photovoltaic Power Station Cluster Control System Simulation Test Report 13
Foreword
This document is in accordance with GB/T 1.1-2020 "Guidelines for Standardization Part 1.Structure and Drafting Rules of Standardization Documents".
To be drafted.
Please note that some of the contents of this document may involve patents. The issuing agency of this document is not responsible for identifying patents.
This document was proposed by the China Electricity Council.
This document is under the jurisdiction of the National Standardization Technical Committee for Microgrid and Distributed Power Grid Connection (SAC/TC564).
Drafting organizations of this document. Southeast University, China Electric Power Research Institute Co., Ltd., Nanjing University of Science and Technology, State Grid Jiangsu Electric Power Co., Ltd.
Company Electric Power Research Institute, State Grid Anhui Electric Power Co., Ltd., Jiangsu Kunyou Energy Technology Co., Ltd., State Grid Jiangsu Electric Power Co., Ltd.,
State Grid Beijing Electric Power Research Institute.
The main drafters of this document. Gu Wei, Sheng Wanxing, Liu Wei, Wu Ming, Li Qiang, Huang Qiang, Pan Jing, Zou Dehu, Lou Guannan, Gu Chenxiao, Li Peixin,
Lv Zhenhua, Sun Lijing, Xu Bin, Cao Ge, Liu Weiqi, Shi Wenbo, Han Huachun, Cao Yang, Lei Zhen, Li Ke, Wei Songtao, Shi Kun, Chen Chang, Jia Dongqiang.
Simulation test of cluster control system of photovoltaic power station in villages and towns
skills requirement
1 Scope
This document specifies the simulation test items, test systems, test procedures and result judgments of the cluster control system of village and town photovoltaic power stations.
This document is applicable to clusters of village and town photovoltaic power plants that are connected to the power grid of 10kV and below.
2 Normative references
The contents of the following documents constitute the indispensable clauses of this document through normative references in the text. Among them, dated quotations
Only the version corresponding to that date is applicable to this document; for undated reference documents, the latest version (including all amendments) is applicable to
This document.
GB/T 36116 Functional requirements for cluster control system of photovoltaic power stations in villages and towns
DL/T 634.5-101 Telecontrol Equipment and System Part 5-101.Transmission Protocol Basic Telecontrol Task Supporting Standard
DL/T 634.5-104 Telecontrol equipment system Part 5-104.Transmission protocol adopts IEC 60870-5- standard transmission protocol set
101 network access
3 Terms and definitions
The terms and definitions defined in GB/T 36116 apply to this document.
4 Basic regulations
4.1 The simulation test of the cluster control system of the village and town photovoltaic power station shall include the functions of monitoring the master station and the monitoring terminal of the cluster control system
test.
4.2 The simulation test of the cluster control system of the village and town photovoltaic power station should be realized through real-time simulation and the tested hardware-in-the-loop test. The real-time simulation department
The sub-should have the ability to simulate power systems and communication systems.
4.3 The simulation test should prepare a test outline, including test items, test steps, test results judgment analysis, etc., and develop safety precautions.
4.4 The simulation test equipment should not be connected to the test power supply from the tested object.
4.5 Before testing, the tested hardware such as the cluster monitoring master station or monitoring terminal, real-time simulation device, and communication simulation system should pass the test system.
The system interface is interconnected, and the typical architecture is shown in Appendix A.
4.6 Data should be recorded during the test. See Appendix B for the record sheet.
4.7 After the test is completed, a simulation test report should be formed. See Appendix C for the simulation test report of the cluster control system of the village and town photovoltaic power station.
4.8 The function test results of the photovoltaic power station cluster control system of the tested villages and towns shall meet the relevant regulations of GB/T 36116.
5 Test items
5.1 Monitoring the main station test project
The test project of the cluster monitoring master station of the village and town photovoltaic power station should include the basic function test and the extended function test of the cluster monitoring master station.
|