Technical requirements of dry process cement production complete equipment -- Part 1: Raw meal preparation system
| Valid |
GB/T 35150.1-2017
|
Standard similar to GB/T 35150.1-2017 GB/T 35150.5 GB/T 35150.6 GB/T 35150.4
Basic data | Standard ID | GB/T 35150.1-2017 (GB/T35150.1-2017) | | Description (Translated English) | Technical requirements of dry process cement production complete equipment -- Part 1: Raw meal preparation system | | Sector / Industry | National Standard (Recommended) | | Classification of Chinese Standard | Q92 | | Classification of International Standard | 91-110 | | Word Count Estimation | 14,149 | | Date of Issue | 2017-12-29 | | Date of Implementation | 2018-11-01 | | Regulation (derived from) | National Standards Bulletin 2017 No. 32 | | Issuing agency(ies) | General Administration of Quality Supervision, Inspection and Quarantine of the People's Republic of China, Standardization Administration of the People's Republic of China |
GB/T 35150.1-2017: Technical requirements of dry process cement production complete equipment -- Part 1: Raw meal preparation system ---This is a DRAFT version for illustration, not a final translation. Full copy of true-PDF in English version (including equations, symbols, images, flow-chart, tables, and figures etc.) will be manually/carefully translated upon your order.
Technical requirements of dry process cement production complete equipment - Part 1. Raw meal preparation system
ICS 91-110
Q92
National Standards of People's Republic of China
New dry process cement production equipment and technical requirements
Part 1. raw meal preparation system
Part 1. Rawmealpreparationsystem
2017-12-29 Posted
2018-11-01 implementation
General Administration of Quality Supervision, Inspection and Quarantine of People's Republic of China
China National Standardization Administration released
Foreword
GB/T 35150 "new dry-process cement production equipment technical requirements" is divided into two parts.
--- Part 1. raw meal preparation system;
--- Part 2. firing system.
This section GB/T 35150 Part 1.
This section drafted in accordance with GB/T 1.1-2009 given rules.
This part is proposed by China Building Materials Federation.
This part of the National Building Materials and Equipment Standardization Technical Committee (SAC/TC465) centralized.
This section is responsible for the drafting unit. Sinoma Equipment Group Co., Ltd., Tianjin Cement Industry Design and Research Co., Ltd..
Participated in the drafting of this section. Chengdu Lijun Industrial Co., Ltd., Hefei, Central Asia Building Materials Equipment Co., Ltd., Jiangsu Pengfei Group Unit
Co., Ltd., Yancheng Institute of Technology, China Building Materials (Hefei) Powder Technology Equipment Co., Ltd., China Building Material Machinery Industry Association, Shanghai New Weight
Machinery Co., Ltd., Sinoma International Research Institute, Anhui Fengxing Wear-resistant Materials Co., Ltd.
The main drafters of this section. Di Dongren, Liu Jikai, Chai Xing Teng, He Xiaoyi, Liu Zhongan, Deng Siwen, Deng Xiaolin, Ye Weidong, Ben Daolin,
Liu Pingcheng, Wang Qianqian, Yin Zhifeng, Wang Yumin, Zhang Rui, Shi Shaoguang, Chen Xiao.
New dry process cement production equipment and technical requirements
Part 1. raw meal preparation system
1 Scope
This section provides a new type of dry process cement production equipment in the raw meal preparation system equipment composition, technical requirements, safety and environmental requirements,
Installation acceptance, commissioning and performance testing and delivery documents.
This section applies to the new dry process cement production equipment in the raw meal preparation system technical requirements.
2 Normative references
The following documents for the application of this document is essential. For dated references, only the dated version applies to this article
Pieces. For undated references, the latest edition (including all amendments) applies to this document.
GB/T 176 Methods of chemical analysis of cement
Test methods for fineness of cement - Method of sieve analysis GB/T 1345-2005
GB .2007.7 bulk mineral products sampling, sample preparation Particle size determination method manual screening method
GB 2894 safety signs and rules of their use
GB/T 3766 Hydraulic System General Specifications
GB/T 3797 electrical control equipment
GB 4064 Electrical Equipment Safety Design Guidelines
GB 4915 Cement Industry Air Pollutant Emission Standard
GB 5226.1 Safety of machinery - Electrical machinery and electronic equipment - Part 1. General specifications
GB/T 7251 (all parts) Low-voltage switchgear and control equipment
GB/T 7932 pneumatic system of general technical conditions
GB/T 7935 hydraulic components General technical conditions
GB/T 8196 mechanical safety devices
GB/T 10595 belt conveyor
GB 14784 belt conveyor safety regulations
GB/T 16754 mechanical safety emergency stop design principles
GB/T 17248.3 acoustic machines and equipment emitting noise work position and other specified positions emission sound pressure level measurement is
Quarantine law
GB 18613-2012 small and medium-sized three-phase asynchronous motor efficiency limits and energy efficiency rating
GB/T 18831 mechanical belt guard interlocking device design and selection principles
GB/T 19670 mechanical safety against accidental start
Heat balance, thermal efficiency and comprehensive energy consumption calculation method of cement rotary kiln GB/T
Determination of heat balance of rotary kilns GB/T
GB/T 26567 cement raw materials wear test method (Bond method)
GB/T 27976 cement industry tube mill equipment
GB/T 27977 energy efficiency testing and calculation of cement production methods
GB/T 50087 Industrial Enterprise Noise Control Design Code
Geotechnical test methods GB/T
Tips & Frequently Asked Questions:Question 1: How long will the true-PDF of GB/T 35150.1-2017_English be delivered?Answer: Upon your order, we will start to translate GB/T 35150.1-2017_English as soon as possible, and keep you informed of the progress. The lead time is typically 1 ~ 3 working days. The lengthier the document the longer the lead time. Question 2: Can I share the purchased PDF of GB/T 35150.1-2017_English with my colleagues?Answer: Yes. The purchased PDF of GB/T 35150.1-2017_English will be deemed to be sold to your employer/organization who actually pays for it, including your colleagues and your employer's intranet. Question 3: Does the price include tax/VAT?Answer: Yes. Our tax invoice, downloaded/delivered in 9 seconds, includes all tax/VAT and complies with 100+ countries' tax regulations (tax exempted in 100+ countries) -- See Avoidance of Double Taxation Agreements (DTAs): List of DTAs signed between Singapore and 100+ countriesQuestion 4: Do you accept my currency other than USD?Answer: Yes. If you need your currency to be printed on the invoice, please write an email to [email protected]. In 2 working-hours, we will create a special link for you to pay in any currencies. Otherwise, follow the normal steps: Add to Cart -- Checkout -- Select your currency to pay.
|