Milestones and activities during commissioning of electrical instrumentation and control systems in the process industry
| Obsolete |
GB/Z 22135-2008
|
PDF similar to GBZ22135-2008
Basic data | Standard ID | GB/Z 22135-2008 (GB/Z22135-2008) | | Description (Translated English) | Milestones and activities during commissioning of electrical instrumentation and control systems in the process industry | | Sector / Industry | National Standard | | Classification of Chinese Standard | N10 | | Classification of International Standard | 25.040.01 | | Word Count Estimation | 27,289 | | Date of Issue | 2008-06-18 | | Date of Implementation | 2009-01-01 | | Adopted Standard | IEC/PAS 62337-2002, IDT | | Regulation (derived from) | ?National Standard Approval Announcement 2008 No.11 (Total No.124) | | Issuing agency(ies) | Ministry of Health of the People's Republic of China | | Summary | This standard specifies the debugging stage and tags. And in cases before the formal description of the activity after " construction " sign, factory acceptance owners conducted. These activities will be applicable to a variety of process/plant. |
GBZ22135-2008: Milestones and activities during commissioning of electrical instrumentation and control systems in the process industry ---This is a DRAFT version for illustration, not a final translation. Full copy of true-PDF in English version (including equations, symbols, images, flow-chart, tables, and figures etc.) will be manually/carefully translated upon your order.
Milestones and activities during commissioning of electrical instrumentation and control systems in the process industry
ICS 25.040.01
N10
People's Republic of China national standardization of technical guidance documents
GB /Z22135-2008/IEC /PAS62337..2002
Process Industry in Electronic Equipment and Control Systems
Marking and activities in debugging
(IEC /PAS 62337..2002, IDT)
2008-06-18 released
2009-01-01 implementation
General Administration of Quality Supervision, Inspection and Quarantine of People's Republic of China
China National Standardization Administration released
Directory
Preface Ⅰ
Introduction Ⅱ
1 Scope 1
2 Definition 1
3 Use of this guidance document 2
4 General Preparation Before Factory Acceptance 2
5 construction is completed 3
6 pre-commissioning (mechanical installation is completed) 3
7 debugging 4
8 Performance Testing and Factory Acceptance 5
Appendix A (Normative) List of Documents Used in Pre-commissioning and Commissioning 7
Appendix B (informative) pre-commissioning activities described 8
Appendix C (Normative) Mechanical Installation Certificate 19
Appendix D (Informative) Debugging Activity Description 20
Appendix E (Normative) Factory Acceptance Certificate 21
Appendix F (normative) special projects 22
GB /Z22135-2008/IEC /PAS62337..2002
Foreword
This Guidance Document is equivalent to IEC /PAS 62337..2002 "Marking of Commissioning of Electronic Equipment and Control Systems in Process Industries
And activities "(in English).
According to GB/T 1.1-2000 "Standardization Guide Part 1. Standard Structure and Writing Rules", delete the IEC /PAS
62337. Preface to.2002.
Appendix A, Appendix C, Appendix E and Appendix F of this guidance document are normative appendices, while Appendix B and Appendix D are informative
appendix.
This guidance document is proposed by China Machinery Industry Federation.
The guidance of technical documents by the National Industrial Process Measurement and Control Standardization Technical Committee second sub-technical committee.
This technical guidance document is drafted by. Southwest University.
The guidance of technical documents Participated in the drafting of. Mechanical Industry Instrumentation Technology and Economy Institute, China Sihe Instrumentation
Mission, Shanghai Automation Instrumentation Co., Ltd., Zhejiang University, Beijing Institute of Machinery Industry Automation.
The main drafters of this technical guidance document. Liu Feng, Lu Jing, Qi Qian.
The drafting of the guidance of technical documents. Feng Xiaosheng, Liu Jin, Zhang Qingjun, Feng Dongqin, Xie Bingbing.
GB /Z22135-2008/IEC /PAS62337..2002
Introduction
In the process industry, there is a clear trend, that is, the entire factory construction tasks with a one-time payment or similar business methods
To the contractor. Past experience has shown that both the process industry (hereafter referred to as the owner) and the contractor will be time-consuming and laborious to discuss their solutions
Undertake activities, scope and their respective responsibilities in the transfer of the factory.
The guidance document has improved and facilitated the consultative process between both parties and has allowed both parties to reach agreement on the scope of their respective activities.
This guidance does not reflect the interests of the pharmaceutical industry or other highly specialized industries.
GB /Z22135-2008/IEC /PAS62337..2002
Process Industry in Electronic Equipment and Control Systems
Marking and activities in debugging
1 Scope
This Guidance Document defines the stages and markups in commissioning (Figure 1) and describes in examples the completion of construction
After that, the owner conducted the activity before the factory acceptance. These activities will be applied to various processes/factories.
Note. Construction and pre-commissioning activities may overlap.
Figure 1 stage and the definition of the mark
2 definition
The following definitions apply to this guidance document.
2.1
A phase during which non-operational corrections, cold test runs, cleaning and mechanical test activities are performed. Specific details refer to attached
Record B.
2.2
A mark indicates that the entire factory or any part of it has been installed in accordance with the drawings, instructions, instructions and application code and
Test, and adjusted to achieve the extent of cold test run. This means that all necessary electrical and instrumentation has been completed.
This mark marks the end of the pretest activity.
2.3
A phase in which media such as water or inert substances are used in place of chemicals for the operation of equipment and plants and
Test activities.
2.4
A mark, marking the end of the cold test. At this moment, the working range of each instrument circuit should be adjusted and can reflect the actual operation
Turn when the work situation.
2.5
A phase in which the chemicals actually used in the process are used to run and test equipment and devices to provide real life
Production ready.
GB /Z22135-2008/IEC /PAS62337..2002
|