Technical requirements of measurement and verification of energy savings -- Communication room project
| Valid |
GB/T 31347-2014
|
PDF similar to GB/T 31347-2014
Basic data | Standard ID | GB/T 31347-2014 (GB/T31347-2014) | | Description (Translated English) | Technical requirements of measurement and verification of energy savings -- Communication room project | | Sector / Industry | National Standard (Recommended) | | Classification of Chinese Standard | F01 | | Classification of International Standard | 27.010 | | Word Count Estimation | 14,191 | | Date of Issue | 12/31/2014 | | Date of Implementation | 7/1/2015 | | Quoted Standard | GB/T 28750-2012 | | Regulation (derived from) | National Standards Bulletin 2014 No. 33 | | Issuing agency(ies) | General Administration of Quality Supervision, Inspection and Quarantine of the People's Republic of China, Standardization Administration of the People's Republic of China | | Summary | This standard specifies the communications room saving technological transformation projects energy savings measurement and verification of energy consumption statistics and border demarcation project scope, basic requirements, measurement and verificatio |
GB/T 31347-2014: Technical requirements of measurement and verification of energy savings -- Communication room project ---This is a DRAFT version for illustration, not a final translation. Full copy of true-PDF in English version (including equations, symbols, images, flow-chart, tables, and figures etc.) will be manually/carefully translated upon your order.
Technical requirements of measurement and verification of energy savings - Communication room project
ICS 27.010
F01
National Standards of People's Republic of China
Energy savings measurement and verification technical requirements
Communications room project
Issued on. 2014-12-31
2015-07-01 implementation
Administration of Quality Supervision, Inspection and Quarantine of People's Republic of China
Standardization Administration of China released
Foreword
This standard was drafted in accordance with GB/T 1.1-2009 given rules.
This standard by the National Standardization Technical Committee for Energy and Management (SAC/TC20) and focal points.
This standard was drafted. Shanghai Broadband Technology Engineering Research Center (National Broadband Network and Application Engineering Research Center), the
National Institute of Standardization, Shandong Computer Science Center (Jinan national supercomputing centers), Shanghai Telecom Co., Ltd., China Telecom Shanghai Research
Hospital, Shanghai Mobile Communications Co., Ltd., Shanghai Research Institute of Posts and Telecommunications Design Consulting Co., Ltd., Shanghai Science and Technology Network Communication Co., Ltd., Shanghai
Municipal Energy Efficiency Center, Oriental Cable Network Co., Ltd., Shenzhen Qianhai Smart Energy Systems Limited.
The main drafters of this standard. Fang Xing, Li Pengcheng, Wang Yansong, Ge Changrong, Chen Hai Hung, Tian Jianwei, Xiayu Juan, Pan Chong Chao, Li Gang, Zhou Wei,
Wu Xiaoming, Li Min, Loujie Liang, Wang Xiaoming, Xie Jing, Ding Bo, Huang Yun, Zhang Yi, Qin Hongbo, Cao Yu, Tan Qian.
Energy savings measurement and verification technical requirements
Communications room project
1 Scope
This standard specifies the communications room saving technological transformation projects energy savings measurement and verification of energy consumption statistics and border demarcation project scope, group
This requires the measurement and verification methods.
This standard applies to the communications room implemented energy-saving projects measurement and verification of energy savings, not for uninterruptible power supply systems
(UPS) expansion project.
2 Normative references
The following documents for the application of this document is essential. For dated references, only the dated version suitable for use herein
Member. For undated references, the latest edition (including any amendments) applies to this document.
GB/T 28750-2012 energy section measurement and verification techniques General
3 Terms and Definitions
GB/T 28750-2012 define the following terms and definitions apply to this document.
3.1
Communications room communicationroom
Install communication equipment placement options, including Internet Data Center (IDC), a communication base stations.
3.2
Communications equipment traffic datatrafficofcommunicationequipment
Within a certain period of time the communication device carried by the incoming and outgoing data throughput data throughput combined.
4 border demarcation project scope and power consumption statistics
4.1 Item border demarcation
The project boundary is divided as shown in FIG.
Tips & Frequently Asked Questions:Question 1: How long will the true-PDF of GB/T 31347-2014_English be delivered?Answer: Upon your order, we will start to translate GB/T 31347-2014_English as soon as possible, and keep you informed of the progress. The lead time is typically 1 ~ 3 working days. The lengthier the document the longer the lead time. Question 2: Can I share the purchased PDF of GB/T 31347-2014_English with my colleagues?Answer: Yes. The purchased PDF of GB/T 31347-2014_English will be deemed to be sold to your employer/organization who actually pays for it, including your colleagues and your employer's intranet. Question 3: Does the price include tax/VAT?Answer: Yes. Our tax invoice, downloaded/delivered in 9 seconds, includes all tax/VAT and complies with 100+ countries' tax regulations (tax exempted in 100+ countries) -- See Avoidance of Double Taxation Agreements (DTAs): List of DTAs signed between Singapore and 100+ countriesQuestion 4: Do you accept my currency other than USD?Answer: Yes. If you need your currency to be printed on the invoice, please write an email to [email protected]. In 2 working-hours, we will create a special link for you to pay in any currencies. Otherwise, follow the normal steps: Add to Cart -- Checkout -- Select your currency to pay.
|