US$439.00 ยท In stock Delivery: <= 4 days. True-PDF full-copy in English will be manually translated and delivered via email. GB/T 19668.6-2019: Information technology service -- Surveillance -- Part 6: Application system: Surveillance specification for the data center project Status: Valid GB/T 19668.6: Evolution and historical versions
Standard ID | Contents [version] | USD | STEP2 | [PDF] delivered in | Standard Title (Description) | Status | PDF |
GB/T 19668.6-2019 | English | 439 |
Add to Cart
|
4 days [Need to translate]
|
Information technology service -- Surveillance -- Part 6: Application system: Surveillance specification for the data center project
| Valid |
GB/T 19668.6-2019
|
GB/T 19668.6-2007 | English | 439 |
Add to Cart
|
3 days [Need to translate]
|
Commissioner of information engineering specification -- Part 6: Engineering Safety Management Regulation
| Obsolete |
GB/T 19668.6-2007
|
PDF similar to GB/T 19668.6-2019
Basic data Standard ID | GB/T 19668.6-2019 (GB/T19668.6-2019) | Description (Translated English) | Information technology service -- Surveillance -- Part 6: Application system: Surveillance specification for the data center project | Sector / Industry | National Standard (Recommended) | Classification of Chinese Standard | L01 | Classification of International Standard | 35.020 | Word Count Estimation | 22,215 | Date of Issue | 2019-08-30 | Date of Implementation | 2020-03-01 | Quoted Standard | GB/T 19668.1-2014 | Issuing agency(ies) | State Administration for Market Regulation, China National Standardization Administration | Summary | This standard specifies the process and related services of data center engineering supervision in the application system. The supervision of computer sites (computer rooms) and other infrastructure is not described in this standard. This standard applies to the supervision services of the bidding, design, implementation and acceptance process of application-oriented data center construction projects. |
GB/T 19668.6-2019: Information technology service -- Surveillance -- Part 6: Application system: Surveillance specification for the data center project ---This is a DRAFT version for illustration, not a final translation. Full copy of true-PDF in English version (including equations, symbols, images, flow-chart, tables, and figures etc.) will be manually/carefully translated upon your order.
Information technology service - Surveillance - Part 6. Application system. Surveillance specification for the data center project
ICS 35.020
L01
National Standards of People's Republic of China
Information Technology Service Supervisor Part 6.
Application System. Data Center Engineering Supervision Specification
Informationtechnologyservice-Surveilance-Part 6. Applicationsystem.
Published on.2019-08-30
2020-03-01 implementation
State market supervision and administration
China National Standardization Administration issued
Content
Foreword I
1 Scope 1
2 Normative references 1
3 Terms and Definitions 1
4 Abbreviations 2
5 Data Center Engineering Supervision Process 2
6 Data Center Engineering Bidding Stage Supervision Activities and Contents 2
6.1 Data Center Engineering Bidding Stage Supervision Activities 2
6.2 Supervision content of the tendering phase of the data center project 3
7 Data Center Engineering Design Stage Supervision Activities and Contents 3
7.1 Data Center Engineering Design Stage Supervision Activities 3
7.2 Supervision content of the data center engineering design stage 4
8 Data Center Engineering Implementation Stage Supervision Activities and Contents 4
8.1 Data Center Engineering Implementation Stage Supervision Activities 4
8.2 Data Center Engineering Information System Software and Hardware Supervision Content 5
8.3 Supervision content of data center information resources (data) 6
8.4 Supervision of data center personnel and related rules and regulations 6
8.5 Contents of the supervision records of the supervisors during the data center implementation phase 6
9 Data Center Engineering Acceptance Phase Supervision Activities and Contents 7
9.1 Data Center Engineering Acceptance Phase Supervision Activity 7
9.2 Supervision Contents of Data Center Engineering Acceptance Phase 7
Appendix A (informative) Procedures for supervision of data center engineering at all stages 9
A.1 Data Center Engineering Bidding Stage Supervision Work Procedure 9
A.2 Data Center Engineering Design Stage Supervision Work Procedures 10
A.3 Data Center Engineering Implementation Stage Supervision Work Procedures 11
A.4 Data Center Engineering Acceptance Phase Supervision Work Procedures 12
Appendix B (informative) Data Center Implementation Process Inspection Record Table 13
B.1 Data Center Information Network System Software and Hardware Inspection Record Table 13
B.2 Data Center Information Application System Software Check Record Table 14
B.3 Data Center Information Resources (Data) Check Record Table 15
B.4 Data Center personnel and corresponding regulatory system inspection records 15
Appendix C (informative) Data Center Engineering Acceptance Record Table 17
C.1 Data Center Engineering Acceptance Record Table 17
C.2 Data Center Engineering Acceptance Test Record Table 18
Reference 19
Foreword
GB/T 19668 "Information Technology Service Supervision" is divided into the following parts.
--- Part 1. General;
--- Part 2. Infrastructure engineering supervision specifications;
--- Part 3. Operation and maintenance supervision specifications;
--- Part 4. Information Security Supervision Specifications;
--- Part 5. Software Engineering Supervision Specifications;
--- Part 6. Application System. Data Center Engineering Supervision Specification;
--- Part 7. Supervisory workload measurement specifications.
This part is the sixth part of GB/T 19668.
This part is drafted in accordance with the rules given in GB/T 1.1-2009.
Please note that some of the contents of this document may involve patents. The issuing organization of this document is not responsible for identifying these patents.
This part is proposed and managed by the National Information Technology Standardization Technical Committee (SAC/TC28).
This section drafted by. China Electronics Technology Standardization Institute, Beijing Zhongbaixin Information Technology Co., Ltd., Beijing Jiaotong University,
Zhejiang Tianhang Consulting Supervision Co., Ltd., Shenzhen Aikeke Engineering Consulting Supervision Co., Ltd., Shenzhen Duxin Construction Supervision Co., Ltd., Ning
Poseidon Information Technology Co., Ltd., Dalian Hongrun Design Consulting Co., Ltd., Beijing Times Dingdian Engineering Consulting Co., Ltd., Beijing Kensett
Information System Consulting Co., Ltd., Shandong Zhengzhong Information Technology Co., Ltd., Shenyang Huaruibo Information Technology Co., Ltd., Beijing North Consulting
Information Engineering Consulting Co., Ltd., Beijing Guoyan Information Engineering Supervision Consulting Co., Ltd., Beijing Lianhai Information System Co., Ltd., Liaoning North Real Estate
Laboratory Co., Ltd., Chengdu Anmeiqin Information Technology Co., Ltd., Xinjiang Tianheng Information System Consulting Management Co., Ltd., Beijing Xida Construction
Set up supervision limited liability company, Huizhou Yixintong Information Technology Service Co., Ltd., Wuhan Shiwei Information Technology Co., Ltd., Hunan Zhizhi
Xin Information Co., Ltd., Information Technology Center of Beijing Foreign Languages Bureau, Beijing Technology and Business University.
Drafters of this section. Zhuo Lan, Lu Xuezhe, Feng Benrui, Li Jiaqi, Guo Xiong, Happy Li, Wen Tingxiang, Jin Hua, Wang Hongquan, Wang Li, Li Lili,
Tu Shuang, Yang Jianbin, Zhang Jiancheng, Shao Hua, Cai Ruogu, Chu Jie, Li Haitao, Wang Bo, Zhao Yi, Tong Qing, Chen Weicong, Ke Hanbo, Huang Huiqiang, Jiao Qingwu,
Liu Wenzhi, Wen Huadong, Wang Bin, Jiang Jiaxuan, Lu Quanli, Zheng Leilei, Liu Chunyu, Liang Haitao, Yuan Ziqiang, Qi Ligang, Song Cheng, Cai Benxin, Tan Guohua,
Xia Chuan, Liu Jun, Lin Huabin, Sun Riping, Song Wei, Ju Xiaoying, Liu Hongzhi, Liu Xuecheng, Jia Zhuosheng, Huang Hong, Ge Yukang.
Information Technology Service Supervisor Part 6.
Application System. Data Center Engineering Supervision Specification
1 Scope
This part of GB/T 19668 specifies the process and related services for data center engineering supervision in the application system. Computer field
The supervision of the house and other infrastructure is not described in this section.
This section applies to the supervision services for the tendering, design, implementation and acceptance of data center construction projects for application systems.
2 Normative references
The following documents are indispensable for the application of this document. For dated references, only dated versions apply to this article.
Pieces. For undated references, the latest edition (including all amendments) applies to this document.
GB/T 19668.1-2014 Information technology service supervision Part 1. General
3 Terms and definitions
The following terms and definitions as defined in GB/T 19668.1-2014 apply to this document.
3.1
Data center datacenter
Supported by information technology, computer field (computer room), other infrastructure, information system hardware and software, information resources (data) and personnel
And the corresponding rules and regulations to achieve centralized application processing and centralized data storage, providing data construction, exchange, integration, sharing
The basic environment of information services.
Note 1. Rewrite GB/T 32910.1-2017, definition 2.1.
Note 2. The data center described in this section does not include the computer site (machine room) and other infrastructure in this definition.
3.2
Service level indicator servicelevelindicator
Parameters used to assess and measure the capabilities of the provider's information technology services.
[SJ/T 11691-2017, definition 3.6]
3.3
Design design
One is organized by the owner unit, and the data center design unit will detail the construction drawings that have passed the review to the contractor and the supervision unit.
Ming's technical activities help contractors and supervisors to correctly implement design intent, master the quality requirements of key engineering sites, and ensure engineering
quality.
3.4
Deepening the design of detaileddesign
On the basis of the original design plan and drawings, the contractor shall, in light of the actual situation on the site, refine, supplement and improve the drawings to form the construction.
The process of designing a document.
|