Pressure pipe supervision inspection regulation
| Valid |
Excerpted PDFs (Download full copy in 9 seconds upon purchase)PDF Preview: TSG D7006-2020
TSG D7006-2020: Pressure pipe supervision inspection regulation---This is an excerpt. Full copy of true-PDF in English version (including equations, symbols, images, flow-chart, tables, and figures etc.), auto-downloaded/delivered in 9 seconds, can be purchased online: https://www.ChineseStandard.net/PDF.aspx/TSGD7006-2020
TSG
TECHNICAL SPECIFICATION FOR
SAFETY OF SPECIAL EQUIPMENT
Pressure pipe supervision inspection regulation
State Administration for Market Regulation
May 16, 2020
Foreword
Table of Contents
Foreword... 2
1 General... 5
2 General requirements... 8
3 Supplementary provisions... 15
Appendix A Special requirements for manufacturing supervision inspection of
pressure piping components... 16
Appendix B Special requirements for supervision inspection of long-distance
pipeline construction... 24
Appendix C Special requirements for construction supervision inspection of
public pipelines... 33
Appendix D Special requirements for supervision inspection of industrial
pipeline construction... 41
Appendix E Special equipment supervision inspection certificate... 50
(Manufacturing of pressure piping components)... 50
Appendix F Notice on special equipment supervision inspection opinion (1). 53
Appendix G Evaluation of implementation status of quality assurance system
... 55
Appendix H Special equipment supervision inspection liaison form... 58
Pressure pipe supervision inspection regulation
1 General
1.1 Purpose
In order to standardize the supervision inspection of pressure piping
components manufacturing (supervision and inspection is hereinafter referred
to as supervision inspection) and the supervision inspection of pressure
pipeline installation, modification and major repairs (installation, modification
and major repairs are hereinafter collectively referred to as construction), in
accordance with the "Special Equipment Safety Law of the People's Republic
of China" "Special Equipment Safety Supervision Regulations", this regulation
is hereby formulated.
1.2 Scope of application
1.2.1 Manufacturing supervision inspection
This regulation is applicable to the supervision inspection of the manufacturing
process of the following pressure piping components within the scope as
specified in the "Special Equipment Catalog".
(1) Submerged arc welded steel pipe, polyethylene pipe (Note 1-1);
(2) Gas pressure regulating device, temperature and pressure reducing
device, factory prefabricated pipe segment (Note 1-2), flow meter (shell)
(Note 1-3) in the component assembly device.
Note 1-1.It excludes polyethylene pipes with metal skeletons and fiber-
reinforced polyethylene pipes.
Note 1-2.Factory prefabricated pipe segment refers to the piping component
products manufactured by the manufacturer after welding and assembling
pressure piping components in the factory according to the construction design
drawings. It does not include the piping prefabrication performed by the
installation organization at the construction site.
Note 1-3.The temperature and pressure reducing devices, factory
prefabricated pipe segments, flow meters (shells) used in the pipelines within
the boiler range can be manufactured, supervisory inspected in accordance
with the relevant regulations of the boiler.
1.2.2 Supervision inspection of construction
This regulation is applicable to the supervision inspection of the following
construction processes of pressure pipelines (long-distance pipelines, public
pipelines and industrial pipelines) within the scope specified in the "Special
Equipment Catalog".
(1) Installation process;
(2) Modification or major repairs (except for emergency pipeline construction
process) (Note 1-4), the process of replacing the pipeline with the same
medium at a time with a total length of more than 100 meters.
Note 1-4.Modification of pressure pipeline refers to an activity that changes
pipeline specifications, materials, structural layout, or changes in pipeline media,
pressure, temperature and other working parameters, resulting in changes in
pipeline performance parameters or pipeline structure.
Major repairs to pressure pipelines refer to the use of welding methods to
replace pipe segments, valves, pipe corrections, welding repairs of pressure
parts, pressure sealing, pressure blocking, etc.
1.3 Basic requirements
Supervision inspection of pressure piping is that based on the qualified self-
inspection of the inspected organization, the inspection agency undertaking the
supervision inspection work (hereinafter referred to as the supervision
inspection agency) shall perform the supervision of the process of
manufacturing of pressure piping components or the construction of pressure
piping [hereinafter referred to as manufacturing (construction)], as well as the
compliance verification to meet basic safety requirements. The supervision
inspection agency and the inspected organization shall sign a supervision
inspection contract, to clarify the responsibilities and obligations of both parties.
Supervision inspection cannot replace the self-inspection of the inspected
organization.
Pressure piping components and pressure piping that shall be subject to
supervision inspection but not supervisory inspected or failed in the supervision
inspection shall not be put into use.
1.4 Inspected organization
The inspected organization refers to the organization whose work quality has a
direct impact on the safety performance of the pressure pipeline during the
manufacturing (construction) process, including the pressure pipeline
component manufacturer and the pressure pipeline construction organization
(or its entrusted organization, the same below), design organization,
construction organization, non-destructive testing organization, etc.
The inspected organization shall do the following work.
1.5 Supervision inspection agencies and supervisory inspectors
1.6 Management requirements
Pressure piping component manufacturers and construction organizations,
design organizations, construction organizations, non-destructive testing
organizations, supervision inspection organizations, etc., shall strictly
implement this Regulation; enter the required data in the special equipment
information management system in a timely manner in accordance with the
requirements on the information management of special equipment safety
technical specifications.
2 General requirements
2.1 Supervision inspection procedures
The supervision inspection procedures generally include acceptance of
applications, preparations for supervision inspections, implementation of
supervision inspections, issuance of supervision inspection certificates.
2.1.1 Acceptance of applications
The pressure piping component manufacturer and building organization (or
construction organization) shall submit the application for the pressure piping
supervision inspection to the supervision inspection agency before
manufacturing or construction.
After the supervision inspection agency accepts the supervision inspection
application, it shall provide the applicant organization with a sample supervision
inspection contract; inform the applicant organization of the list of relevant
materials that need to be provided.
2.2 Supervision inspection work content and methods
2.2.1 Supervision inspection work content
(1) Through the supervision inspection of the process that has an impact on
the safety performance of the pressure piping, carry out the compliance
verification of the manufacturing process of the pressure piping
components, the construction process of the pressure piping, whether the
results meet the requirements of the safety technical specifications;
(2) Evaluate the implementation status of the quality assurance system of the
manufacturing (construction) organization.
2.2.2 Supervision inspection method
Supervision inspection generally adopts methods such as document review,
physical inspection and on-site supervision. The specific requirements are as
follows.
2.4 Supervision inspection report of construction
The supervision inspection report of pressure pipeline construction shall include
at least the following contents.
2.5 Archive of supervision inspection data
After the supervision inspection work is completed, the supervision inspection
agency shall classify, label, catalog the supervision inspection materials in a
timely manner; establish files. The period of retention of the supervision
inspection materials shall not be less than the service life of the pressure
pipeline.
3 Supplementary provisions
3.1 Dispute handling
During the supervision inspection process, when a dispute arises between the
inspected organization and the supervision inspection agency, it can apply
handling to the municipal special equipment safety supervision department
where the pressure pipeline components are manufactured or where the
pressure pipeline construction is located.
3.2 Interpretation permissions
The State Administration for Market Regulation is responsible for the
interpretation of this Regulation.
3.3 Implementation time
This Regulation will come into effect on September 1, 2020.The ��Regulations
on the safety and quality supervision inspection of pressure piping installation��
(GZJG [2002] No.83) promulgated by the former General Administration of
Quality Supervision, Inspection and Quarantine, "Pressure piping unit
manufacture supervision inspection regulation (submerged-arc welding steel
pipe and polyethylene pipe)" (TSG D7001-2005), ��Pressure piping unit
manufacture supervision inspection regulation�� (TSG D7001-2013) shall be
repealed at the same time.
...... Source: Above contents are excerpted from the full-copy PDF -- translated/reviewed by: www.ChineseStandard.net / Wayne Zheng et al.
Tips & Frequently Asked QuestionsQuestion 1: How long will the true-PDF of English version of TSG D7006-2020 be delivered?Answer: The full copy PDF of English version of TSG D7006-2020 can be downloaded in 9 seconds, and it will also be emailed to you in 9 seconds (double mechanisms to ensure the delivery reliably), with PDF-invoice. Question 2: Can I share the purchased PDF of TSG D7006-2020_English with my colleagues?Answer: Yes. The purchased PDF of TSG D7006-2020_English will be deemed to be sold to your employer/organization who actually paid for it, including your colleagues and your employer's intranet. Question 3: Does the price include tax/VAT?Answer: Yes. Our tax invoice, downloaded/delivered in 9 seconds, includes all tax/VAT and complies with 100+ countries' tax regulations (tax exempted in 100+ countries) -- See Avoidance of Double Taxation Agreements (DTAs): List of DTAs signed between Singapore and 100+ countriesQuestion 4: Do you accept my currency other than USD?Answer: Yes. www.ChineseStandard.us -- TSG D7006-2020 -- Click this link and select your country/currency to pay, the exact amount in your currency will be printed on the invoice. Full PDF will also be downloaded/emailed in 9 seconds.
How to buy and download a true PDF of English version of TSG D7006-2020?A step-by-step guide to download PDF of TSG D7006-2020_EnglishStep 1: Visit website https://www.ChineseStandard.net (Pay in USD), or https://www.ChineseStandard.us (Pay in any currencies such as Euro, KRW, JPY, AUD). Step 2: Search keyword "TSG D7006-2020". Step 3: Click "Add to Cart". If multiple PDFs are required, repeat steps 2 and 3 to add up to 12 PDFs to cart. Step 4: Select payment option (Via payment agents Stripe or PayPal). Step 5: Customize Tax Invoice -- Fill up your email etc. Step 6: Click "Checkout". Step 7: Make payment by credit card, PayPal, Google Pay etc. After the payment is completed and in 9 seconds, you will receive 2 emails attached with the purchased PDFs and PDF-invoice, respectively. Step 8: Optional -- Go to download PDF. Step 9: Optional -- Click Open/Download PDF to download PDFs and invoice. See screenshots for above steps: Steps 1~3 Steps 4~6 Step 7 Step 8 Step 9
|