HAD00201-2019 English PDFHAD00201: Historical versions
Basic dataStandard ID: HAD 002/01-2019 (HAD002/01-2019)Description (Translated English): (Emergency preparation and emergency response of nuclear power plant operating unit) Sector / Industry: Chinese Industry Standard HAD002/01-2010
Annex I.
Nuclear Safety Guideline HAD 002/01-2010
Emergency Preparedness and Emergency Response
Operating Unit of Nuclear Power Plant
Approved & Issued by National Nuclear Safety Administration
on August 20, 2010
(Approval version)
National Nuclear Safety Administration
Emergency Preparedness and Emergency Response
Operating Unit of Nuclear Power Plant
(Approved by National Nuclear Safety Administration for release on
August 20, 2010)
This Guideline shall be implemented from August 20, 2010
This Guideline shall be interpreted by National Nuclear Safety
Administration
This Guideline is a guiding document. Methods and programs different from this Guideline
may be adopted in practical work; however, it must be proved that the methods and
programs adopted are of safety level at least same as this Guideline.
Annexes of this Guideline are reference documents.
Table of Contents1. Introduction ... 7 1.1 Purpose ... 7 1.2 Scope ... 7 2 Development of Emergency plans and Related Documents ... 8 2.1 Requirements of operating units or related units for emergency plans and emergency response at different stages ... 8 2.2 Formulation of emergency plan ... 10 2.3 Emergency plan execution program ... 11 2.4 Coordination of emergency plans ... 11 3 Emergency Organizations ... 11 3.1 Main responsibilities and basic organizational structure of emergency organizations ... 12 3.2 Emergency headquarter and the responsibilities ... 12 3.3 Operational on-duty responsible-person ... 13 3.4 Emergency action group ... 13 3.5 Interface with off-site emergency response organizations ... 15 4 Emergency state and emergency action level ... 16 4.1 Emergency State Grading ... 16 4.2 Emergency action level ... 19 5 Emergency planning zone ... 19 5.1 Principles of determining emergency planning zone ... 19 5.2 Determination of emergency planning zone ... 20 5.3 Emergency planning zone of multi-reactor plant site ... 20 6 Emergency Facilities and Emergency Equipment ... 21 6.1 Overview ... 21 6.2 Master control room ... 21 6.3 Auxiliary control room ... 21 6.4 Emergency control center ... 21 6.5 Technical support center ... 22 6.6 Operational support center ... 22 6.7 Public information center ... 23 6.8 Communication system ... 23 6.9 Monitoring and evaluation facilities ... 24 6.10 Protective facilities ... 25 6.11 First aid and medical facilities ... 25 6.12 Emergency evacuation routes and assembly points ... 25 6.13 Residence requirements ... 25 7 Emergency Response and Protective Measures ... 26 7.1 Overview ... 26 7.2 Intervention principle and intervention level ... 26 7.3 Response actions under emergency state ... 27 7.4 Emergency notification ... 28 7.5 Evaluation activities ... 28 7.6 Remedial action ... 29 7.7 Protective measures ... 29 7.8 Emergency exposure control ... 30 7.9 Medical rescue ... 31 8 Emergency Termination and Recovery Action ... 32 8.1 Termination of emergency state ... 32 8.2 Recovery action ... 32 9 Maintaining of Emergency Response Capacity ... 33 9.1 Training ... 33 9.2 Drills ... 33 9.3 Maintenance of emergency facilities and equipment ... 34 9.4 Emergency plan review and modification ... 34 10 Records and Reports ... 34 10.1 Records ... 34 10.2 Reports ... 35 10.3 Final evaluation report of accident ... 36 Glossary ... 37 Annex A Requirements for Emergency Operation in Site-selection Phase ... 39 A.1 General requirements ... 39 A.2 Use of regional land and water... 39 A.3 Population distribution ... 39 A.4 Consideration on feasibility of emergency plan ... 39 Annex B Format and Content of On-site Emergency Plan of Nuclear Power Plant ... 42 B.1 General provisions ... 42 B.2 Overview of nuclear power plant and the environment ... 42 B.3 Emergency planning zone ... 42 B.4 Emergency state classification and emergency action level ... 42 B.5 Emergency organizations and responsibilities ... 42 B.6 Emergency facilities and equipment ... 43 B.7 Emergency communication, reporting and notification ... 44 B.8 Emergency operation control and system equipment rush repair ... 44 B.9 Accident consequence evaluation ... ......Tips & Frequently Asked Questions:Question 1: How long will the true-PDF of HAD00201-2019_English be delivered?Answer: Upon your order, we will start to translate HAD00201-2019_English as soon as possible, and keep you informed of the progress. The lead time is typically in 9 seconds (download/delivered in 9 seconds). The lengthier the document the longer the lead time.Question 2: Can I share the purchased PDF of HAD00201-2019_English with my colleagues?Answer: Yes. The purchased PDF of HAD00201-2019_English will be deemed to be sold to your employer/organization who actually pays for it, including your colleagues and your employer's intranet.Question 3: Does the price include tax/VAT?Answer: Yes. Our tax invoice, downloaded/delivered in 9 seconds, includes all tax/VAT and complies with 100+ countries' tax regulations (tax exempted in 100+ countries) -- See Avoidance of Double Taxation Agreements (DTAs): List of DTAs signed between Singapore and 100+ countriesQuestion 4: Do you accept my currency other than USD?Answer: Yes. If you need your currency to be printed on the invoice, please write an email to Sales@ChineseStandard.net. In 2 working-hours, we will create a special link for you to pay in any currencies. Otherwise, follow the normal steps: Add to Cart -- Checkout -- Select your currency to pay.Question 5: Should I purchase the latest version HAD00201-2019?Answer: Yes. Unless special scenarios such as technical constraints or academic study, you should always prioritize to purchase the latest version HAD00201-2019 even if the enforcement date is in future. Complying with the latest version means that, by default, it also complies with all the earlier versions, technically. |