GB/Z 22135-2008RFQ ASK 4 days Milestones and activities during commissioning of electrical instrumentation and control systems in the process industry Obsolete

Similar standards

GB/T 20438.5   GB/T 20438.4   GB/T 20438.3   GB/T 20965   GB/T 41771.6   GB/T 45510   

Basic data

Standard ID: GB/Z 22135-2008 (GB/Z22135-2008)
Description (Translated English): Milestones and activities during commissioning of electrical instrumentation and control systems in the process industry
Sector / Industry: National Standard
Classification of Chinese Standard: N10
Classification of International Standard: 25.040.01
Word Count Estimation: 27,289
Date of Issue: 2008-06-18
Date of Implementation: 2009-01-01
Adopted Standard: IEC/PAS 62337-2002, IDT
Regulation (derived from): ?National Standard Approval Announcement 2008 No.11 (Total No.124)
Issuing agency(ies): Ministry of Health of the People's Republic of China
Summary: This standard specifies the debugging stage and tags. And in cases before the formal description of the activity after " construction " sign, factory acceptance owners conducted. These activities will be applicable to a variety of process/plant.

GBZ22135-2008: Milestones and activities during commissioning of electrical instrumentation and control systems in the process industry


---This is a DRAFT version for illustration, not a final translation. Full copy of true-PDF in English version (including equations, symbols, images, flow-chart, tables, and figures etc.) will be manually/carefully translated upon your order.
Milestones and activities during commissioning of electrical instrumentation and control systems in the process industry ICS 25.040.01 N10 People's Republic of China national standardization of technical guidance documents GB /Z22135-2008/IEC /PAS62337..2002 Process Industry in Electronic Equipment and Control Systems Marking and activities in debugging (IEC /PAS 62337..2002, IDT) 2008-06-18 released 2009-01-01 implementation General Administration of Quality Supervision, Inspection and Quarantine of People's Republic of China China National Standardization Administration released Directory Preface Ⅰ Introduction Ⅱ 1 Scope 1 2 Definition 1 3 Use of this guidance document 2 4 General Preparation Before Factory Acceptance 2 5 construction is completed 3 6 pre-commissioning (mechanical installation is completed) 3 7 debugging 4 8 Performance Testing and Factory Acceptance 5 Appendix A (Normative) List of Documents Used in Pre-commissioning and Commissioning 7 Appendix B (informative) pre-commissioning activities described 8 Appendix C (Normative) Mechanical Installation Certificate 19 Appendix D (Informative) Debugging Activity Description 20 Appendix E (Normative) Factory Acceptance Certificate 21 Appendix F (normative) special projects 22 GB /Z22135-2008/IEC /PAS62337..2002

Foreword

This Guidance Document is equivalent to IEC /PAS 62337..2002 "Marking of Commissioning of Electronic Equipment and Control Systems in Process Industries And activities "(in English). According to GB/T 1.1-2000 "Standardization Guide Part 1. Standard Structure and Writing Rules", delete the IEC /PAS 62337. Preface to.2002. Appendix A, Appendix C, Appendix E and Appendix F of this guidance document are normative appendices, while Appendix B and Appendix D are informative appendix. This guidance document is proposed by China Machinery Industry Federation. The guidance of technical documents by the National Industrial Process Measurement and Control Standardization Technical Committee second sub-technical committee. This technical guidance document is drafted by. Southwest University. The guidance of technical documents Participated in the drafting of. Mechanical Industry Instrumentation Technology and Economy Institute, China Sihe Instrumentation Mission, Shanghai Automation Instrumentation Co., Ltd., Zhejiang University, Beijing Institute of Machinery Industry Automation. The main drafters of this technical guidance document. Liu Feng, Lu Jing, Qi Qian. The drafting of the guidance of technical documents. Feng Xiaosheng, Liu Jin, Zhang Qingjun, Feng Dongqin, Xie Bingbing. GB /Z22135-2008/IEC /PAS62337..2002

Introduction

In the process industry, there is a clear trend, that is, the entire factory construction tasks with a one-time payment or similar business methods To the contractor. Past experience has shown that both the process industry (hereafter referred to as the owner) and the contractor will be time-consuming and laborious to discuss their solutions Undertake activities, scope and their respective responsibilities in the transfer of the factory. The guidance document has improved and facilitated the consultative process between both parties and has allowed both parties to reach agreement on the scope of their respective activities. This guidance does not reflect the interests of the pharmaceutical industry or other highly specialized industries. GB /Z22135-2008/IEC /PAS62337..2002 Process Industry in Electronic Equipment and Control Systems Marking and activities in debugging

1 Scope

This Guidance Document defines the stages and markups in commissioning (Figure 1) and describes in examples the completion of construction After that, the owner conducted the activity before the factory acceptance. These activities will be applied to various processes/factories. Note. Construction and pre-commissioning activities may overlap. Figure 1 stage and the definition of the mark

2 definition

The following definitions apply to this guidance document. 2.1 A phase during which non-operational corrections, cold test runs, cleaning and mechanical test activities are performed. Specific details refer to attached Record B. 2.2 A mark indicates that the entire factory or any part of it has been installed in accordance with the drawings, instructions, instructions and application code and Test, and adjusted to achieve the extent of cold test run. This means that all necessary electrical and instrumentation has been completed. This mark marks the end of the pretest activity. 2.3 A phase in which media such as water or inert substances are used in place of chemicals for the operation of equipment and plants and Test activities. 2.4 A mark, marking the end of the cold test. At this moment, the working range of each instrument circuit should be adjusted and can reflect the actual operation Turn when the work situation. 2.5 A phase in which the chemicals actually used in the process are used to run and test equipment and devices to provide real life Production ready. GB /Z22135-2008/IEC /PAS62337..2002
......
Image     

Tips & Frequently Asked Questions:

Question 1: How long will the true-PDF of GBZ22135-2008_English be delivered?

Answer: Upon your order, we will start to translate GBZ22135-2008_English as soon as possible, and keep you informed of the progress. The lead time is typically 2 ~ 4 working days. The lengthier the document the longer the lead time.

Question 2: Can I share the purchased PDF of GBZ22135-2008_English with my colleagues?

Answer: Yes. The purchased PDF of GBZ22135-2008_English will be deemed to be sold to your employer/organization who actually pays for it, including your colleagues and your employer's intranet.

Question 3: Does the price include tax/VAT?

Answer: Yes. Our tax invoice, downloaded/delivered in 9 seconds, includes all tax/VAT and complies with 100+ countries' tax regulations (tax exempted in 100+ countries) -- See Avoidance of Double Taxation Agreements (DTAs): List of DTAs signed between Singapore and 100+ countries

Question 4: Do you accept my currency other than USD?

Answer: Yes. If you need your currency to be printed on the invoice, please write an email to Sales@ChineseStandard.net. In 2 working-hours, we will create a special link for you to pay in any currencies. Otherwise, follow the normal steps: Add to Cart -- Checkout -- Select your currency to pay.