US$755.00 · In stock · Download in 9 secondsGB 50303-2015: Code for acceptance of construction quality of building electrical engineering Delivery: 9 seconds. True-PDF full-copy in English & invoice will be downloaded + auto-delivered via email. See step-by-step procedureStatus: Valid GB 50303: Evolution and historical versions
Standard ID | Contents [version] | USD | STEP2 | [PDF] delivery | Name of Chinese Standard | Status |
GB 50303-2015 | English | 755 |
Add to Cart
|
0-9 seconds. Auto-delivery
|
Code for acceptance of construction quality of building electrical engineering
| Valid |
GB 50303-2002 | English | 95 |
Add to Cart
|
0-9 seconds. Auto-delivery
|
Code for acceptance of construction quality of electrical installation in building
| Obsolete |
Excerpted PDFs (Download full copy in 9 seconds upon purchase)PDF Preview: GB 50303-2015
GB 50303-2015: Code for acceptance of construction quality of building electrical engineering---This is an excerpt. Full copy of true-PDF in English version (including equations, symbols, images, flow-chart, tables, and figures etc.), auto-downloaded/delivered in 9 seconds, can be purchased online: https://www.ChineseStandard.net/PDF.aspx/GB50303-2015
GB
NATIONAL STANDARD OF THE
PEOPLE’S REPUBLIC OF CHINA
UDC
P GB 50303-2015
Code for Acceptance of Construction Quality of Building
Electrical Engineering
Issued on. DECEMBER 3, 2015
Implemented on. AUGUST 1, 2016
Issued by. Ministry of Housing and Urban-Rural Construction of the People’s
Republic of China;
General Administration of Quality Supervision, Inspection and
Quarantine of the People’s Republic of China.
NATIONAL STANDARD OF THE
PEOPLE’S REPUBLIC OF CHINA
Code for Acceptance of Construction Quality of Building
Electrical Engineering
Developed by. Zhejiang Housing and Urban-Rural Construction Department
Approved by. Ministry of Housing and Urban-Rural Development of the People's Republic
of China
Implementation Date. August 1, 2016
China Planning Press
2015 Beijing
Announcement of the Ministry of Housing and Urban-Rural
Development of the People's Republic of China
No. 994
Table of Contents
Foreword... 4
1 General Provisions... 10
2 Terms and Symbols... 11
3 Basic Requirements... 14
4 Installation of Transformer and Box-type Distribution Station... 28
5 Installation of Complete Set Distribution Cabinet, Control Cabinet (Console, Box),
Distribution Box (Switch Board)... 31
6 Check the Wiring of Electromotor, Electrical Heater and Electric Actuating Machine
7 Installation of Diesel Power Generating Set... 39
8 Installation of UPS and EPS... 41
9 Testing and Power Test Run of Electrical Equipment... 43
10 Installation of Busway... 44
11 Installation of Ladder, Tray and Trunking... 48
12 Conduit Laying... 51
13 Cable Laying... 56
14 Conduit Wiring and Trunking Wiring... 60
15 Straight Laying of Plastic Sheathed Wire... 62
17 Cable Head Production, Wire Connection and Line Insulation Test... 66
18 Installation of Ordinary Luminaire... 69
19 Installation of Special Luminaire... 74
20 Installation of Switch, Socket and Fan... 79
21 Power Test Run of Building Lighting... 83
22 Installation of Earthing Device... 84
23 Earthing Busbar Laying in Electricity Transformation and Distribution Room and
Electrical shaft... 86
24 Installation of Lightning Down-conductor and Air-termination... 88
25 Equipotential Bonding of Buildings... 91
Appendix A Subdivisional Work and Inspection Lot of Subdivisional Project... 92
Appendix B Generator Handover Testing... 94
Appendix C Low-voltage Apparatus Handover Testing... 96
Appendix D Overlapping Size of Busbar Blot... 97
Appendix E Tightening Torque of Bolt Lapped Busbar... 99
Appendix F Minimum Net Distance between Busway, Ladder, Tray, Trunking and
Pipeline 100
Appendix G Minimum Distance between Conduit / Wiring Trunking and Hot-water
Pipe and Steam Pipe... 101
Appendix H Tightening Torque of Crew-type Terminal... 102
Explanation of Wording in This Code... 103
List of Quoted Standards... 104
Code for Acceptance of Construction Quality of Building
Electrical Engineering
1 General Provisions
1.1.1 This code is formulated with a view to strengthening the quality management of
construction engineering, unifying the construction quality acceptance of building electrical
engineering and ensuring the engineering quality.
1.1.2 This code is applicable to the construction quality acceptance of building electrical
installation project with voltage class of 35kV or below.
1.1.3 Building electrical engineering construction quality acceptance shall meet those
specified in this code as well as the current relevant ones of the nation.
2 Terms and Symbols
2.1 Terms
2.1.1 Wiring system
Combination composed of one or more insulated wire, cable or busbar and its fixed part and
mechanical protection part.
2.1.2 Current-using equipment
Electrical equipment used for converting electric energy into energies of other types.
2.1.7 SELV system
Electrical system non-earthed under normal condition and with voltage not exceeding extra-
low voltage.
2.1.8 PELV system
Electrical system earthed under normal condition and with voltage not exceeding extra-low
voltage.
2.1.9 FELV system
Electrical system with the voltage necessary not for safety but for operation not exceeding extra-
low voltage.
2.2 Symbols
SPD——Surge protection device;
IMD——Insulation monitoring device;
UPS——Uninterrupted power supply;
EPS——Emergency power supply.
3 Basic Requirements
3.1 General Requirements
3.2 Site Acceptance of Main Equipment, Materials, Finished Product and Semi-
finished Products
3.2.1 Main equipment, materials, finished product and semi-finished products shall be
subjected to site acceptance, and acceptance record shall be kept and acceptance data shall be
filed. In case there are technical parameter requirements for design, the technical parameter
shall be checked and meet the design requirements.
3.2.2 Products with production license or compulsory certification (CCC certification) shall be
provided with license No. or CCC certification mark, and certification scope, effectiveness and
3.3 Confirmation of Process Handover
3.3.1 Installation of transformer and box-type substation shall meet the following
requirements.
4 Installation of Transformer and Box-type Distribution Station
4.1 Dominant Item
4.1.1 As for transformer installation, the position shall be correct and the accessories shall
be complete; in case of oil-immersed transformer, the oil level shall be normal without oil
leakage.
Inspection quantity. total inspection.
Inspection method. visual inspection.
4.1.2 Earthing connection mode and earthing resistance value of transformer neutral point
shall meet the design requirements
4.2 General Item
4.2.1 The lubrication of drive part of load voltage regulating switch shall be in good
condition, the action shall be flexible, the inching given position and the actual position of
switch shall be in consistent; the automatic regulation shall meet the requirements of the
product technical documents.
4.2.2 Insulating piece shall be free from cracks, defects, and damages to porcelain elements
and porcelain glazes; the outward appearance shall be clean; thermo-detector shall show
accurately.
5 Installation of Complete Set Distribution Cabinet, Control
Cabinet (Console, Box), Distribution Box (Switch Board)
5.1 Dominant Item
5.1.1 Metal frame and basic profile steel of cabinet, console and box shall be reliably
connected to protective conductor; as for openable door equipped with electrical device,
earthing terminals of door and metal frame shall be connected by yellow-green insulated
copper-cored flexible wire with the sectional area not less than 4mm2 and marked with
identification.
5.2 General Item
5.2.1 Permissible installation deviation of basic profile steel shall be in accordance with
those specified in Table 5.2.1.
5.2.2 Arrangement and safety clearance of cabinet, platform, box and switch board shall
meet the design requirements.
6 Check the Wiring of Electromotor, Electrical Heater and Electric Actuating Machine
6.1 Dominant Item
6.1.1 Exposed-conductive-part of electromotor, electrical heater and electric actuating
machine must be reliably connected to protective conductor.
6.1.2 Insulation resistance value of low voltage motor, electrical heater and electric
actuating machine shall not be less than 0.5MΩ.
6.1.3 Handover test of high-voltage motor and electromotor with voltage above 100kW
shall meet the requirements of the current national standard Standard for Hand-over Test of
Electric Equipment Electric Equipment Installation Engineering (GB 50150).
6.2 General Item
6.2.1 Electrical equipment shall be installed firmly; bolts and anti-looseness parts shall be
complete without looseness. Wiring inlet and junction box cover of moisture-proof electrical
equipment shall be subjected to sealing treatment.
7 Installation of Diesel Power Generating Set
7.1 Dominant Item
7.1.1 Test of the generator shall meet those specified in Appendix B of this code.
7.1.2 As for phase-to-phase insulation resistance value and phase to earth insulation
resistance value of feeder line from power generating set to distribution cabinet, it shall not be less
than 0.5 MΩ for low voltage feeder line and it shall not be less than 1MΩ/kV for high voltage
feeder line; DC withstand voltage test of insulated cable feeder line shall meet the
requirements of the current national standard Standard for Hand-over Test of Electric Equipment
Electric Equipment Installation Engineering (GB 50150).
7.2 General Item
7.2.1 Wiring of random distribution cabinet or control cabinet of power generating set shall be
correct, fasteners shall be fastened without omission or shedding. Model and specification of
switch and protective device shall be correct; lock mark of end-of-manufacturing test shall be
verified to be without displacement, in case there is displacement, and it shall be re-tested
and calibrated.
7.2.2 Switchgear of distribution cabinet on the power receiving side, automatic or manual
switching device and protective device shall pass the test and shall be subjected to load test
according to the application allocation scheme of the designed self-contained power supply.
Diesel power generating set shall operate continuously without failure.
8 Installation of UPS and EPS
8.1 Dominant Item
8.1.1 Rectification and inversion of UPS and EPS, static switch as well as specification and
model of energy storage battery or storage battery set shall meet the design requirements.
Internal wiring shall be correct and reliable without looseness, and fasteners shall be complete.
8.1.2 Polarity of UPS and EPS shall be correct; the tests and adjustments on such technical
performance indexes as the stability of actuations of all-level input/output protection system and
output voltage, waveform distortion factor, frequency, phase and actuation of static switch shall
meet the requirements of technical product documents. In case end-of-manufacturing test is
replaced by on-site final test, test adjustment shall be carried out according to product technical
documents and shall meet the requirements of the design documents.
8.1.3 EPS shall be subjected to the following inspections according to design requirements or
requirements of product technical documents.
8.1.5 Connection mode for system earthing of UPS output terminal shall meet the design
requirements.
8.2 General Item
8.2.1 As for rack or metallic base for placing UPS, it shall be assembled straightly and
evenly, the fasteners shall be complete, and the permissible deviation of levelness and verticality
shall not be greater than 1.5 ‰.
8.2.3 Exposed-conductive-part of UPS and EPS shall be reliably connected to protective
conductor and shall possess identification.
Inspection quantity. 20% of the total number of equipment shall be randomly inspected and the
quantity of randomly inspected equipment shall not be less than 1.
Inspection method. Carry out visual inspection.
8.2.4 Noise of Α-weighted sound level generated by UPS during normal operation shall
meet the requirements of product technical documents.
9 Testing and Power Test Run of Electrical Equipment
9.1 Dominant Item
9.1.1 Relevant electrical equipment and line shall be tested qualified according to the
specification of this code before power test run.
9.2 General Item
9.2.1 The operation voltage and current of electric power equipment and each instrument
reading shall be normal.
Inspection quantity. Total inspection. Inspection
method. Carry out visual inspection.
9.2.2 The actuation direction and indication of electrical actuator shall be consistent with
the design requirements of process device.
Inspection quantity. 10% of the total number of equipment shall be randomly inspected and the
quantity of the randomly inspected equipment shall not be less than 1.
Inspection method. Carry out visual inspection.
...... Source: Above contents are excerpted from the full-copy PDF -- translated/reviewed by: www.ChineseStandard.net / Wayne Zheng et al.
Tips & Frequently Asked QuestionsQuestion 1: How long will the true-PDF of English version of GB 50303-2015 be delivered?Answer: The full copy PDF of English version of GB 50303-2015 can be downloaded in 9 seconds, and it will also be emailed to you in 9 seconds (double mechanisms to ensure the delivery reliably), with PDF-invoice. Question 2: Can I share the purchased PDF of GB 50303-2015_English with my colleagues?Answer: Yes. The purchased PDF of GB 50303-2015_English will be deemed to be sold to your employer/organization who actually paid for it, including your colleagues and your employer's intranet. Question 3: Does the price include tax/VAT?Answer: Yes. Our tax invoice, downloaded/delivered in 9 seconds, includes all tax/VAT and complies with 100+ countries' tax regulations (tax exempted in 100+ countries) -- See Avoidance of Double Taxation Agreements (DTAs): List of DTAs signed between Singapore and 100+ countriesQuestion 4: Do you accept my currency other than USD?Answer: Yes. www.ChineseStandard.us -- GB 50303-2015 -- Click this link and select your country/currency to pay, the exact amount in your currency will be printed on the invoice. Full PDF will also be downloaded/emailed in 9 seconds. Question 5: Should I purchase the latest version GB 50303-2015?Answer: Yes. Unless special scenarios such as technical constraints or academic study, you should always prioritize to purchase the latest version GB 50303-2015 even if the enforcement date is in future. Complying with the latest version means that, by default, it also complies with all the earlier versions, technically.
How to buy and download a true PDF of English version of GB 50303-2015?A step-by-step guide to download PDF of GB 50303-2015_EnglishStep 1: Visit website https://www.ChineseStandard.net (Pay in USD), or https://www.ChineseStandard.us (Pay in any currencies such as Euro, KRW, JPY, AUD). Step 2: Search keyword "GB 50303-2015". Step 3: Click "Add to Cart". If multiple PDFs are required, repeat steps 2 and 3 to add up to 12 PDFs to cart. Step 4: Select payment option (Via payment agents Stripe or PayPal). Step 5: Customize Tax Invoice -- Fill up your email etc. Step 6: Click "Checkout". Step 7: Make payment by credit card, PayPal, Google Pay etc. After the payment is completed and in 9 seconds, you will receive 2 emails attached with the purchased PDFs and PDF-invoice, respectively. Step 8: Optional -- Go to download PDF. Step 9: Optional -- Click Open/Download PDF to download PDFs and invoice. See screenshots for above steps: Steps 1~3 Steps 4~6 Step 7 Step 8 Step 9
|